About the project: This project is the first 1,000-tonne modern domestic waste incineration power plant in China, with a total investment of RMB 670 million. Three waste incineration treatment lines are set up, each with a capacity of 15.2t/h and a daily treatment capacity of 1,000 tonnes, equipped with two sets of 8,800kw steam turbine generators. The main process sections are: rubbish unloading and storage area, incineration boiler area, turbine power generation area, flue gas purification area and auxiliary systems, supporting public works and so on.
Service scope of CME: CME and its mother company are responsible for the supervision of the project equipment. The project supervision department is set up a in Pudong, Shanghai. The system of responsibility of the superintendent engineer is implemented and professional supervision task group of different majors are established, in order to ensure the project’s successful acceptance.